Full-Scale Work Underway Beyond the Arctic Circle!!

The phased modernization of the “Arktika” Ice Palace in Norilsk is in full swing, with a critical stage—the concreting of the technological slab—nearing completion.

After pouring, the concrete slab must cure for 28 days to achieve its required physical properties. During this period, the formwork is dismantled, and surface grinding begins to prepare for the application of a white polymer coating. Simultaneously, work begins on the installation of PROSTOR’s injury-safe boards, securely mounted into pre-prepared foundation inserts.

Meeting the Highest Standards

Achieving international quality standards is PROSTOR’s mission. Achieving high athletic performance is the mission of professional athletes preparing to compete on our ice.

Professionally preparing ice for professional athletes!